410
K
Gross floor area
22
storeys
Above grade
26
mo
Ground-break to handover
2
wk
Ahead of contract date
Project details
No.
02
Client
City of Seattle
Location
Seattle, WA
Sector
Civic
Area
86,000 sq ft
Year
2024
Services
General Contracting
Architect
Northline Architects
A public library, council chamber and waterfront plaza for the City of Seattle, built on reclaimed land and opened on the date the city announced two years earlier.
The challenge
The site is reclaimed harbor land with a high water table, bordered on two sides by a live waterfront promenade that the city wanted kept open through the summer season.
The opening date was public before we were appointed. Any slip would have been visible to every resident, so the schedule had no hidden float to lean on.
Our approach
We split the work into an early ground package and the main build. Ground improvement ran ahead of the main contract, so the structure started on firm, dry ground instead of waiting on it.
Dewatering and ground improvement completed before the main contract mobilized.
A phased promenade closure, so the waterfront stayed open all summer.
Weekly public updates published alongside the client report, written in plain language.
On a civic project the client is the whole city. We reported to residents the same way we report to the council: every week, with the real numbers.

Rebar crews on the council chamber columns, with the promenade open alongside.
The outcome
Harbor Civic Center opened to the public on schedule in spring 2024 and achieved LEED Gold certification. The promenade closures finished two weeks earlier than planned.
The project led to our permanent Seattle office, opened in 2026 to serve civic and commercial clients across the Pacific Northwest.
Gallery
From the core
to the crown.
Progress photography from ground-break to handover, shot by our site team every Friday.





14 days
Ahead of contract handover
Client review
A public project that opened on the day we announced it two years earlier.

Dana Whitfield
Capital Projects, City of Seattle
Next project
Request an estimate
Have a project?
Let's build it.
Tell us about your site, timeline and budget. You'll get a clear, fixed estimate within 10 business days — no obligation.